District Three Construction Leon County Last Updated April 28, 2008 E-mail construction questions regarding District Three here. Construction In Progress Interstate 10 (State Road 8) Leon County - Tallahassee, Florida: Multi-lane construction on I-10 from west of CR 155/Meridian Road to E. of SR 261/Capital Circle. Project began October 2006. Anderson Columbia, Contractor. 3.9 miles; $60.5 million. Anticipated completion, August 2009. Visit the Web site. Interstate 10 (State Road 8) Leon County - Tallahassee, Florida: Multi-lane construction on I-10 from the pavement changes west of CR 361 to west of CR 155 (Meridian Road). Archer Western Contracting, Contractor. 2.8 miles; $54.3 million. Anticipated completion, December 2008. Visit the Web site. Interstate 10 (State Road 8) Leon County - Tallahassee, Florida: Multi-lane construction on I-10 from east of the Rest Areas to the pavement change west of CR 361. C W. Roberts Contracting, Contractor. 3.9 miles; $37.7 million. Anticipated completion, March 2009. Visit the Web site.