Technical Description of the A-12 Avenger
The Demise of the A-12 Avenger
The Restoration of the A-12 Avenger FSM
Technical Description |
The following information is provided courtesy of the Aviation Heritage Association which is building the Aviation Heritage Museum of North Texas at Alliance Airport. The centerpieces of the museum will be a the A-12 Avenger mockup and a rebuilt B-36. |
Prime Contractors
|
Type
|
Power Plant
|
Armament
|
Avionics
|
Dimensions
|
Program Status
|
The Demise of the A-12 Avenger |
The Navy's A-12 Avenger Advanced Technology Aircraft (ATA) was slated
to replace current A-6s on aircraft carriers in the mid-1990's.
Plans for the Navy's A-12 combat aircraft called for incorporating more
advanced stealthy characteristics than were used in the F-117A, as well
as significantly greater payload capabilities.
But on 7 January 1991, Secretary of Defense Richard Cheney canceled the program, in the largest contract termination in DoD history. By one estimate the A-12 had become so expensive that it would have consumed up to 70 percent of the Navy's aircraft budget within three years. The Navy originally planned to buy 620 of the McDonnell Douglas/General Dynamics aircraft, with the Marine Corps purchasing an additional 238 planes. And the Air Force at one point considered buying 400, at an average cost that was estimated at close to $100 million each. The A-12 was designed to fly faster and further than the A-6E, and carry a large bomb-load in internal bomb-bays to reduce drag and maintain a low radar cross-section. As with the Advanced Tactical Fighter (ATF), the A-12 was expected to have greater reliability than current aircraft (double that of the A-6E), and require half the maintenance manhours. The A-12 proved to be the most troubled of the new American stealth aircraft in large part because of problems found in the extensive use of composites in its structure. These composites did not result in anticipated weight savings, and some structural elements had to be replaced with heavier metal components. The weight of each aircraft exceeded 30 tons, 30% over design specification, and close to the limits that could be accommodated on aircraft carriers. The program also experienced problems with its complex Inverse Synthetic Aperture Radar system, as well as delays in its advanced avionics components. The full scope of these problems were not appreciated at the time of Defense Secretary Cheney's Major Aircraft Review, which slowed the production rate and dropped 238 Marine Corps aircraft, leaving the original total Navy buy of 620 aircraft. Cheney also decided to delay for over 5 years the Air Force buy (from 1992 to 1998), which was decoupled from the Navy project. Subsequently, the A-12 contractors revealed that the project faced serious engineering problems and a $2 billion cost overrun, which would delay the first flight by over a year, to the fall of 1991, and raised the unit cost substantially. At first blush, the A-12's performance capabilities would have been in roughly the same class as existing aircraft. The key improvement over existing aircraft, not inherently obvious when comparing specifications, was stealth. While today's radar can detect existing naval aircraft at a range of 50 miles, the A-12 was designed to remain undetected until approximately 10 miles away. This would result in significant operational and survival benefits for the A-12 since defenders would have little opportunity to engage the aircraft once detected so close to the target. The A-12's reduced radar cross section would have been derived, in part, from carrying its ordnance internally. While the top speed of the more visible F/A-18 and A-6 would be significantly reduced by the drag induced by external weapons carriage, the internal weapons bay on the A-12 would provide no impediment to speed. Because it is doubtful that upgraded existing aircraft will be able to fulfill all of the A-12s requirements, Navy officials decided to get fresh bids for a new A-12, dubbed the AX. The Navy estimates the AX to cost $150 million per unit as opposed to the A-12's $165 million price tag. In FY 1992, the AX program will receive over $100 million. To facilitate this program's implementation, the Navy reportedly quizzed the Air Force on how it resurrected the B-1 after President Carter's cancellation. The AX's capabilities were scaled back from those of the A-12. The AX could be termed "A-12 lite" as its range, payload, and particularly its stealth requirements will all be more modest than those of the A-12. The Navy has emphasized the strike role at the expense of the air-to-air mission in the new program, rather than trying to "cover all the bases" and produce an aircraft that could perform numerous roles -- the ambition that proved to be the A-12's undoing. |
A-12 Restoration Update |
The A-12 restoration program has been underway since 1994 under the direction of the
Fort Worth Aviation Heritage Association. The program is currently undergoing the restoration
of engineering hardware which was originally built under the Advanced Tactical Aircraft (ATA)
program to support the development of the A-12 strike aircraft. This hardware consists of a full
scale design aid, full scale powerplant, and crew station flight simulator.
The A-12 full scale design aid is a representation of the A-12 aircraft as it was configured during the Full Scale Development (FSD) program. It was used primarily for assessing the general compatibility of equipment and systems and for demonstration of equipment access and removal, mechanical systems operation, ground servicing and support equipment interface verification. Background In 1993, the Fort Worth Aviation Heritage Association contacted General Dynamics and expressed an interest in acquiring the A-12 engineering hardware for display in the museum to be built at Alliance Airport. A work plan and proposal were prepared by Chuck Herndon and Ed Petrushka and submitted to Robert Wright of General Dynamics. After extensive discussions and coordination with GD security and the Navy, Mr. Wright approved the work plan and proposal and the title transfer was provided to the Fort Worth Aviation Heritage Association. The hardware was declassified by the Navy in early 1994 signaling the beginning of the restoration program. Status Significant progress has been made towards restoring and preparing the hardware for movement to Alliance Airport. A team of ex-General Dynamics employees and Lockheed Martin employees was assembled and, under the direction of Jack Briggs, have continuously worked to prepare the A-12 hardware for display and eventual movement to Alliance Airport. The A-12 restoration team consists of Leon Caison, FX Crump, Jorge Delmonte, Pete Grissel, Chuck Hemdon, Jim Norton, Larry Pamelli, Tris Pollard, Edward Walters, and Marvin Wood. A progress summary is presented in the following paragraphs. Aircraft Full Scale Design Aid Delivery of the aircraft full scale design aid was accomplished during October 1994. Since then the aircraft has undergone a facelift in the form of minor repairs, modifications, and painting. The aircraft full scale design aid was moved to a paint facility in October 1995 to be painted with the original colors intended for the prototype aircraft. The crew station of the aircraft has also had significant restoration and rework to create the original cockpit layout which was to have been used in the development of the A-12. This effort started in February 1995 and as of April 1996, about 90% of the instrumentation has either been completed or fit checked into the cockpit. The forward crew station displays and instruments have all been complete and are awaiting installation into the aircraft. The aft crew station instruments and displays are still in work and should near completion by the summer of 1996. Work in the aircraft weapons bay is progressing slowly. Efforts are underway the build dummy AIM-120 missiles and MK-82 munitions in order to install them in the bay to depict the operational configuration of these items. Completion is slated for November or December of 1996. In order to allow the aircraft external lights to be operational, modification efforts are under way to permit the aircraft to be powered from a conventional external power cart in lieu of using facility power. This effort has been under review since January 1995. Aircraft Powerplant Minor modification were made to the engine display stand to install the exhaust nozzle adapter onto the exhaust section of the engine. With the cooperation of General Electric Aircraft Engines, a cross section of the engine was obtained and work is under way to create a display plaque to highlight the major components and sections of the engine. Crew Station Flight Simulator The crew station flight simulator was utilized during the life of the program to validate aircraft and pilot vehicle interface mechanizations. The simulator is about 50% completed. The forward crew station displays and instruments are near completion and should be ready for installation by September. The aft crew station instruments and displays are still in work and should near completion by year's end. The flight simulator will be utilized as a hands-on exhibit once displayed in the Aviation Heritage Museum to allow the general public to get a feel for the crew station room and realistic feel of displays and controls. When completed, the crew station in the flight simulator will be identical in configuration the crew station restored in the aircraft full scale design aid. |
Back to the Habu Home Page...